A and B together can complete a piece of work in 2 days. If A works for 1 day and B works for 4 days, the work is completed. How much time will B take to complete that work alone?

Subject: Mathematics | Topic: Arithmetic | Difficulty: MEDIUM

Options

  1. (A) 8 days
  2. (B) 6 days
  3. (C) 10 days
  4. (D) 4 days

Verified Answer

Option (B): 6 days