A and B together can complete a piece of work in 2 days. If A works for 1 day and B works for 4 days, the work is completed. How much time will B take to complete that work alone?
Subject: Mathematics | Topic: Arithmetic | Difficulty: MEDIUM
Options
- (A) 8 days
- (B) 6 days
- (C) 10 days
- (D) 4 days
Verified Answer
Option (B): 6 days
Practice complete mock tests for SSC, Banking & Railway exams at https://testx.in/questions/01a0bf72-383f-794e-8c9a-7d871af1180a/a-and-b-together-can-complete