A can complete a piece of work in 16 days. B is 60% more efficient than A. How much time will A and B take together to complete that work?

Subject: Mathematics | Topic: Arithmetic | Difficulty: MEDIUM

Options

  1. (A) 6 2/13 days
  2. (B) 3 2/7 days
  3. (C) 4 3/13 days
  4. (D) 5 4/7 days

Verified Answer

Option (A): 6 2/13 days