Three workers are employed to complete a task costing Rs.1,200. Worker A alone can complete the same work in 8 days, worker B alone in 12 days and worker C alone in 16 days. With the help of a fourth worker, they all together complete the same work in 3 days. How much should the fourth worker be paid out of the total amount?

Subject: Mathematics | Topic: Arithmetic | Difficulty: MEDIUM

Options

  1. (A) Rs.222
  2. (B) Rs.226
  3. (C) Rs.225
  4. (D) Rs.221

Verified Answer

Option (C): Rs.225